[Technique]
A modification of a logical relationshipSee also precedence relationship. A dependency between two p... More that allows an acceleration of the successor activityThe schedule activity that follows a predecessor activity, a... More. For example, in a finish-to-startAlso FS. The logical relationship where initiation of work o... More dependencySee Logical Relationship. More with a ten-day lead, the successor activityThe schedule activity that follows a predecessor activity, a... More can start ten days before the predecessor activityThe schedule activity that determines when the logical succe... More has finished. A negative lead is equivalent to a positive lag[Technique]
A modification of a logical relationship that... More. See also lag[Technique]
A modification of a logical relationship that... More.