[Technique]
A modification of a logical relationshipSee also precedence relationship. A dependency between two p... More that directs a delay in the successor activityThe schedule activity that follows a predecessor activity, a... More. For example, in a finish-to-startAlso FS. The logical relationship where initiation of work o... More dependencySee Logical Relationship. More with a ten-day lag, the successor activityThe schedule activity that follows a predecessor activity, a... More cannot start until ten days after the predecessor activityThe schedule activity that determines when the logical succe... More has finished. See also lead[Technique]
A modification of a logical relationship that... More.