Also called SFScheduled Finish Date More. The logical relationshipSee also precedence relationship. A dependency between two p... More where completionWhen it is agreed that a project or part of a project has be... More of the successorA successor is an activity whose start and finish depends on... More scheduleSee project schedule and see also schedule model. The timing... More activityA component of work performed during the course of a project... More is dependent upon the initiationThe process of committing the organisation to begin a projec... More of the predecessorAn activity that must be completed (or be partially complete... More scheduleSee project schedule and see also schedule model. The timing... More activityA component of work performed during the course of a project... More. See also logical relationshipSee also precedence relationship. A dependency between two p... More.