A process applied to projects to ensure that resources are used as efficiently as possible. It involves utilising float within the project or increasing or decreasing the resources required for specific activities, such that any peaks and troughs of resource usage are smoothed out. This does not affect the project duration. It is also known as time limited scheduling.