Down-Menu*/ .nav li ul {position: absolute; padding: 20px 0; width: 300px;}

Also LS. In the critical path method, the latest possible point in time that a schedule activity may begin based upon the schedule network logic, the project completion date, and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project completion date. The late start dates are determined during the backward pass calculation of the project schedule network.