Generally, but not always, the sequence of scheduleSee project schedule and see also schedule model. The timing... activities that determines the durationAlso DU or DUR. The total number of work periods (not includ... of the projectA temporary endeavour undertaken to create a unique product,.... It is the longest path through the projectA temporary endeavour undertaken to create a unique product,.... See also critical path methodology[Technique]
Also CPM. A schedule network analysis techniq.... This is the line connecting the start of a planning network with the final activityA component of work performed during the course of a project... in that network through those activities with the smallest floatAlso called slack. See total float and free float.. Often this is a line through the network connecting those activities with a zero floatZero float is a condition where there is no excess time betw..., i.e. those activities where any delay will delay the time of the entire network. The series of tasks from the beginning of a projectA temporary endeavour undertaken to create a unique product,... up to its end that takes the longest time. This is also the shortest time in which all tasks in the projectA temporary endeavour undertaken to create a unique product,... can be completed. By definition, no taskThe smallest indivisible part of an activity when it is brok... on the critical path can have any slack timeThe amount of time a task can be extended or delayed before .... In other words, no taskThe smallest indivisible part of an activity when it is brok... on the critical path can be delayed or extended without affecting the finishing date of the projectA temporary endeavour undertaken to create a unique product,.... More information